Carnegie Mellon University School of Business

Carnegie Mellon University School of Business - Pittsburgh, Pennsylvania

Owner: Carnegie Mellon University
Architect: Loyson & Kreuthmeir
C.M./ G.C.: MBM Contracting
Contract Amount: $245,000
Completion Date: 2007

Carnegie Mellon University Cafe

Carnegie Mellon University Cafe - Pittsburgh, Pennsylvania

Owner: Carnegie Mellon
Architect: Springboard Architecture
C.M./G.C.: Rycon Construction
Contract Amount: $211,000
Completion Date: 2007

Geneva College Main Building

Geneva College Science & Engineering Building - Beaver Falls, Pennsylvania

Owner: Geneva College
Architect: WTW Architect
C.M./ G.C.: Jendoco
Contract Amount: 2050000
Completion Date: 2007

Orlando Federal Courthouse

Orlando Federal Courthouse - Orlando, Florida

Owner: GSA
Engineer: HLM Design - Joint Venture
C.M./G.C. Hensel Phelps Construction
Contract Amount: $6,300,000
Completion Date: 2007

Southeast Correctional Institute

Southeast Correctional Institute - Columbus, Ohio

Owner: State of Ohio, Ohio Dept. of Rehabilitation & Corrections
Engineer: Limbach Engineering & Design Services
C.M./G.C.: Limbach
Contract Amount: $1,497,000
Completion Date: 2007

University of Pittsburgh Cathedral

University of Pittsburgh Cathedral - Pittsburgh, Pennsylvania

Owner: University of Pittsburgh
Architect: DRS Architects
C.M./ G.C.: P.J Dick
Contract Amount: $719,300
Completion Date: 2007

FDIC VA Square, Phase II

FDIC VA Square PH II - Arlington, Virginia

Owner: FDIC
C.M./ G.C.: Turner Construction
Contract Amount: $9,290,446
Completion Date: 2006

Pentagon Library & Conference Center

Pentagon Library & Conference Center - Arlington, Virginia

Owner: Dept. Of Defense
Architect: BBGM
C.M./ G.C.: Coakley Williams
Contract Amount: $75,888,000
Completion Date: 2006

FAMU College of Law

Florida A&M College of Law -Tallahassee, Florida

Owner: FAMU
Engineer: TLC
C.M./G.C.: Turner Construction Company
Contract Amount: $2,715,170
Completion Date: 2005

Federal Deposit Insurance Corporation

Federal Deposit Insurance Corporation Office Tower - Arlington, Virginia

Owner:
Architect: Ai
Engineer: Tolk
C.M./G.C.: Turner Construction
Contract Amount: $9,010,000
Completion Date: 2005

Tavares High School

Tavares High School - Tavares, Florida

Owner: Lake County Schools
Engineer: TLC
C.M./G.C.: AJAX
Contract Amount: $1,900,000
Completion Date: 2005

CAPA

CAPA (Creative & Performing Arts) - Pittsburgh, Pennsylvania

Owner: CAPA
Architect: MacLachlan, Cornelius & Filoni, Inc.
Engineer: Firsching, Marstiller, Rusbarsky & Wolf
C.M./G.C.: Mascaro
Contract Amount: $3,315,000
Completion Date: 2004

Coleman USP II

Coleman USP-II, Maximum Security Prison - Coleman, Florida

Owner: FBOP
Architect: DLR
Engineer: DLR, Inc./MPS - Limbach
C.M./G.C.: Clark Construction
Contract Amount: $13,600,000
Completion Date: 2004

Gwinnett County Criminal Justice Expansion

Gwinnett County Criminal Justice Expansion - Atlanta, Georgia

Owner: Gwinnett County Board Of Commissioners
Architect: Rosser International
Engineer: Rosser International
C.M./G.C.: Ellis- Don Construction Company
Contract Amount: $1,100,000
Completion Date: 2004

Utoy Creek WRC Improvement

Utoy Creek WRC Improvement - Atlanta, Georgia

Owner: City of Atlanta
Architect: Brown & Caldwell Consultants/
Williams/Russell & Johnson, Inc.
Engineer: Williams/Russell & Johnson, Inc.
C.M./G.C.: Pizzagalli Construction/ Integral
Contract Amount: $2,400,000
Completion Date: 2004

W&J College Residence Hall

W&J College Residence Hall #2 - Pittsburgh, Pennsylvania

Owner/Developer Capstone Development, Inc.
Architect: RSH Architects
C.M./G.C.: Mascaro
Contract Amount: $590,000
Completion Date: 2004

DEOMI - Patrick Airforce Base

DEOMI - Patrick Air Force Base, Florida

Owner: US Army Corp of Engineers
Engineer: BEK
C.M./G.C.: Rush Construction
Contract Amount: $1,900,000
Completion Date: 2003

Falkenberg Jail

Falkenberg Jail - Hillsborough County, Florida

Owner: Hillsborough County
Engineer: Mechanical Professional Services - Limbach
C.M./G.C.: The Haskell Company
Contract Amount: $6,900,000
Completion Date: 2003

First Church, Publishing House

First Church, Publishing House - Boston, Massachusetts

Owner: First Church of Christ, Scientist
Architect: ADD, Inc.
C.M./G.C.: Shawmut Design & Construction
Contract Amount: $1,400,000
Completion Date: 2003

Geneva College Science & Engineering

Geneva College Science & Engineering Building - Pittsburgh, Pennsylvania

Owner: Geneva College
Architect: WTW Architects
Engineer: Limbach Design & Engineering Services
C.M./G.C.: Jendoco
Contract Amount: $1,900,000
Completion Date: 2003

Holocaust Memorial Center

Holocaust Memorial Center - West Bloomfield, Michigan

Owner: Holocaust Memorial Center
Architect: Neumann Smith
Engineer: Limbach Design & Engineering Services
C.M./G.C.: Granger Construction
Contract Amount: $1,200,000
Completion Date: 2003

Jacksonville Federal Courthouse

Jacksonville Federal Courthouse - Jacksonville, Florida

Owner: Skanska Building USA
Engineer: HLM
C.M./G.C.: Brasfield & Gorrie
Contract Amount: $10,250,000
Completion Date: 2003

Center for Creative Play

Center for Creative Play - Pittsburgh, Pennsylvania

Owner: Center for Creative Play
Architect: Astorino
C.M./G.C.: TEDCO Construction Corporation
Contract Amount: $325,000
Completion Date: 2002

Embry Riddle Aeronautical School

Embry Riddle Aeronautical University - NTES Expansion & Chilled Water
Daytona Beach, Florida

Owner: Embry Riddle Aeronautical University
Engineer: Limbach Design & Engineering Services
C.M./G.C.: Aviation Constructors, Inc.
Contract Amount: $1,400,000
Completion Date: 2002

Embry Riddle Aeronautical University

Embry Riddle Aeronautical University – School Aviation - Daytona Beach, Florida

Owner: Embry Riddle Aeronautical University
Engineer: Energy Systems Design
C.M./G.C.: Aviation Constructors, Inc.
Contract Amount: $725,000
Completion Date: 2002

WSU School of Pharmacy

WSU School of Pharmacy - Detroit, Michigan

Owner: Wayne State University
Architect: Neumann Smith
Engineer: Limbach Design & Engineering Services
C.M./G.C.: Turner Construction
Contract Amount: $8,600,000
Completion Date: 2002

Coleman USP I

Coleman USP-I - Coleman, Florida

Owner: FBOP
Architect: DLR
Engineer: DLR, Inc./Limbach Design & Engineering Services
C.M./G.C.: Clark Construction
Contract Amount: $11,609,062
Completion Date: 2001

Detroit Science Center

Detroit Science Center - Detroit, Michigan

Owner: Detroit Science Center
Architect: Neumann Smith
C.M./G.C.: Walbridge Aldinger
Contract Amount: $2,300,000
Completion Date: 2001

McKay Bay Refuse

McKay Bay Refuse to Energy Retrofit - Tampa, Florida

Owner: City of Tampa
C.M./G.C.: Whiting Turner Construction Co.
Contract Amount: $3,400,000
Completion Date: 2001